Project Description
Building - Chapel
Project Name - South Elevation & Fountain Work
Project Manager - Bill Kerbusch bkerbusc@bw.edu, Ron Bokan rbokan@bw.edu
Office Phone - 826-2235, 826-8186
Duration - April 21st through 7/18/08
Description - The south elevation will be cleaned, repaired and sealed. This will be Phase III of this project. The chapel fountain stone work will be repaired and will undergo a water overhaul for the system.